Client:

Gavin Breeze

Contract Value:

£1,800,000

Start Date:

September 2010

Duration:

78 weeks

Architect:

Hudson Architects

Engineer:

Ross-Gower Associates

Quantity Surveyor:

Tillyard

Form of Contract:

IFC 2005 revision 2 2009

Project:

Hameau d'Orge

Brief Description:

The construction of a new detached house with garages together with external works consisting of road access, bin store, boundary walls and fences, gates, car parking, court yard paving, landscaping and mains installation.

For a Project Overview PDF, please click on the link below:-

 HameauDOrge.pdf